Construction Tables and Calculators
(metric)
![]()
ROGER JOHNSON CONSULTING LIMITED.
|
|
|||||||||||||
| Material Density [kg/m3] |
Depth [millimetres] | ||||||||||||
| 20 | 40 | 50 | 60 | 80 | 100 | 120 | 140 | 160 | 180 | 200 | 220 | 240 | |
| 1,100 | 22 | 44 | 55 | 66 | 88 | 110 | 132 | 154 | 176 | 198 | 220 | 242 | 264 |
| 1,200 | 24 | 48 | 60 | 72 | 96 | 120 | 144 | 168 | 192 | 216 | 240 | 264 | 288 |
| 1,300 | 26 | 52 | 65 | 78 | 104 | 130 | 156 | 182 | 208 | 234 | 260 | 286 | 312 |
| 1,400 | 28 | 56 | 70 | 84 | 112 | 140 | 168 | 196 | 224 | 252 | 280 | 308 | 336 |
| 1,500 | 30 | 60 | 75 | 90 | 120 | 150 | 180 | 210 | 240 | 270 | 300 | 330 | 360 |
| 2,000 | 40 | 80 | 100 | 120 | 160 | 200 | 240 | 280 | 320 | 360 | 400 | 440 | 480 |
| 2,100 | 42 | 84 | 105 | 126 | 168 | 210 | 252 | 294 | 336 | 378 | 420 | 462 | 504 |
| 2,200 | 44 | 88 | 110 | 132 | 176 | 220 | 264 | 308 | 352 | 396 | 440 | 484 | 528 |
| 2,300 | 46 | 92 | 115 | 138 | 184 | 230 | 276 | 322 | 368 | 414 | 460 | 506 | 552 |
| 2,400 | 48 | 96 | 120 | 144 | 192 | 240 | 288 | 336 | 384 | 432 | 482 | 528 | 576 |
| 2,500 | 50 | 100 | 125 | 150 | 200 | 250 | 300 | 350 | 400 | 450 | 500 | 550 | 600 |
| 3,000 | 60 | 120 | 150 | 180 | 240 | 300 | 360 | 420 | 480 | 540 | 600 | 660 | 720 |
Formula used for calculation is: q=(D*W)/1000
q=quantity of material in k/m2
D=depth in millimetres
W=density of material in kg/m3
To calculate total amount of material required for the job(Q), you have to multiply quantity of material (q) with the total area (A) in square metres, as per: Q=q*A
For guideline on various asphalt pavement densities please refer to this page.
![]()
ROGER JOHNSON CONSULTING LIMITED.
BRANCH OFFICE: (604) 888-2099
Send mail to webmaster@rjcsolutions.com
with questions or comments about this web site.
Copyright © 2000 Roger Johnson Consulting Limited.
Last modified: April 19, 2000
| HOME | SITE INDEX |